• By default, the start windows is 0 days. This means that the event can only be completed on the day that it is due. By adjusting the start window, you can allow users to complete the event early.

    • E.g. A start window of 2 days for an event scheduled for a Friday allows the user to complete the event on Wednesday, Thursday, or Friday. The event is available to the user 2 days before the due date.

  • If you have a start window larger than 0, Beacon will send an email notification to the user the first day the user can complete the event.